72MW Liquid-Cooled Data Center
Dallas, TX
Dallas, TX
Dallas, TX
72MW data center project—the FIRST liquid-to-chip deployment for this client. The first 9MW liquid-cooled data hall was delivered on an accelerated schedule, working nearly around-the-clock for 6 weeks, to accomplish commissioning two weeks early.